Reconstruction of 40bay 15kV network switching station
Scope of works:
- preparing the executive designs,
- making the lighting installation and sockets,
- construction of earthing installation,
- making the alarm, fire and Gazex system
- installing the 40bays of the ZX0 switching station,
- installing the cabinets for: telemechanics, communication, RPW220V DC and RPW 230/400V AC,
- complex startup--measurement works.
ZX0 switchgear from ABB
Ex-BEL_Z protections from ELKOMTECH
MST-2 controller from ELKOMTECH
RPW 220V DC from APS